Area: 34,000 sq. ft.
Mandate: Construction Management
Schedule: 5 months (2008)
“As our construction manager, your skill in managing the sub-trades, designers and engineers ensured that, with very few adjustments, we would complete this project successfully. As a client, through your detailed documentation of meetings, billings, construction schedules and change orders, we were always aware of all issues as well as their potential impact on time and cost.”
- Steven Ste. Croix, Vice-President, Operations
Location:
1001 de Maisonneuve Blvd.W., Montreal, Quebec. 10th, 11th & 12th (partial) floors
Client: Standard Life Investments & Standard Life
Architect: Lemay & Associates
Owner: Standard Life
Photographer: Claude-Simon Langlois